Equipment scope

An overhead concrete skip transfers concrete from the supply point to the casting area. A rail-mounted spreader places it along the beam mould. The route and discharge arrangement are selected around the beam geometry and casting sequence.

  • Concrete supply and receiving positions
  • Rail travel, clearances and cleaning access
  • Spreader discharge and layer placement
  • Coordination with moulds, reinforcement and vibration

Configuration inputs

  • Beam drawings and concrete mix
  • Batch demand and casting sequence
  • Mixer location, mould positions and overhead clearances

Equipment limits, utilities, controls and acceptance requirements are confirmed in the project technical package.

Related production solution