A buyer with plate in stock, or a mill contact that beats the fabricator's price, often asks for the steel to be supplied as free issue. The arithmetic looks simple: take the material out of the quoted price and the order gets cheaper.
What changes is who owns the material while it sits on someone else's floor, who proves what it is after cutting, and who absorbs the delay when a plate arrives late or wrong. None of that is settled by the drawing.
Why buyers free issue the steel
The motives are usually commercial rather than technical. A plant may hold surplus plate from an earlier project and want to use it before it rusts. A group may have a frame agreement with a mill that gives better terms than any single fabricator can obtain. A main contractor may be obliged to supply material of a stated origin, and in rail work the end client sometimes specifies the heat.
Supplying a plate to a fabricator is not the same transaction as buying a finished weldment. One is a bailment of goods, the other is a supply of work and materials, and the obligations that follow differ in ways that only show up when something goes wrong.
Whether a given fabricator accepts free issue at all is a commercial decision. Some do routinely, some price it reluctantly, and some decline because the material control burden outweighs the margin. That answer belongs in the first exchange, not in the purchase order.
What a fabricator owes on material it does not own
Once plate is accepted onto the shop floor, the fabricator is holding property that belongs to someone else. Quality management practice treats this as customer property: it has to be identified, verified, protected and safeguarded while in custody, and any loss, damage or unsuitability has to be reported rather than worked around.
In practice that means four things a buyer should expect to see.
- Segregation. Buyer material is stored apart from the fabricator's own stock and marked as such, so it cannot be issued to another job by mistake.
- Receipt records. Quantity, dimensions, heat numbers and condition at arrival, with photographs where the condition is arguable.
- Controlled issue. The cut plan names which plate a part came from, so the link between a component and its certificate survives cutting.
- A reporting route. If a plate is laminated, out of tolerance or simply the wrong grade, the fabricator stops and tells the buyer instead of finding a use for it.
None of it is exotic, but it costs time, and a quote that ignores it will be beaten by one that skips it.
Certificate type is the first thing to fix
Most arguments about free issue steel are arguments about paperwork, and most of those start because the enquiry said "mill certificate" without saying which kind.
EN 10204 defines four inspection document types, and they prove very different things.
| Type | What it contains | Who validates it |
|---|---|---|
| 2.1 | Declaration of compliance with the order, no test results | Manufacturer |
| 2.2 | Compliance plus results from non-specific inspection | Manufacturer |
| 3.1 | Results of specific inspection on the delivered lot | Manufacturer's inspection representative, independent of production |
| 3.2 | As 3.1, with the results also validated by the purchaser's representative or a designated inspector | Manufacturer plus outside inspector |
A 2.1 certificate tells you the mill promised the steel meets the order. It carries no test values. A 3.1 certificate carries chemistry and mechanical results for the heat that was actually delivered, signed by someone outside the production department.
The trap with free issue is that the buyer already holds a certificate that looks authoritative. It may be a 3.1 for the heat, issued to the buyer's own purchase order, which proves what the mill delivered to the buyer but not that the plate the fabricator received came from that heat. If the buyer wants EN 10204 3.1 evidence at handover of the finished weldment, the requirement has to be stated at enquiry, including what happens to the certificate when a plate is split across two orders. A 3.2 document needs its witnessing arranged before the tests happen, because it cannot be created later from an existing 3.1.
Verification at goods in
The single most useful check is also the cheapest: does the heat number on the certificate match the marking on the plate? A certificate that cannot be tied to the physical item proves nothing about that item.
A workable receiving routine looks like this. Record the delivery against the buyer's dispatch note. Check dimensions and thickness against the drawing requirement, not against what the driver says. Match heat numbers across certificate, marking and packing list. For alloy or stainless grades, run positive material identification on a sample, because documents and metal can part company at a stockholder. Photograph the marking while the plate is still intact. Quarantine anything that fails and notify the buyer in writing before cutting.
That last step matters more than it looks. Once the plate is nested and cut, the evidence that would have settled a grade dispute is in the offcut bin.
Cutting loss, offcuts and the remainder
Free issue moves the yield question to the centre of the commercial discussion. When the fabricator buys the plate, cutting loss is inside the price and nobody argues about it. When the buyer supplies it, the loss becomes visible, and someone has to decide who owns it.
Three numbers should be agreed before nesting.
- The allowance for cutting loss and test pieces, expressed as a percentage of net part weight rather than a vague phrase.
- What happens to offcuts above a stated size: returned, credited, or retained by the fabricator.
- Who pays for a replacement plate if a nesting error scraps a part, and how quickly that replacement has to arrive.
A fabricator quoting on free issue assumes a loss allowance it considers normal for the part family. If the buyer's allowance is tighter, the difference reappears in the hourly rate or in a note about rework.
Delivery sequence and storage
Buyer material that arrives early becomes the fabricator's storage problem, and storage is not free even when nobody invoices for it. Plate stacked in a yard for three months picks up surface corrosion, loses its marking under handling, and occupies space that the fabricator planned to use for another order.
The enquiry should state the delivery point, the delivery window, and the sequence relative to the fabrication programme. A single delivery of all plate is simple for the buyer and awkward for the shop; phased deliveries cost more in freight but reduce double handling.
Ask who insures the material in custody, and from which date. Ask what happens if the project slips and the plate sits for six months, and whether it will be stored indoors. These unglamorous questions decide whether the arrangement saves money or moves a cost somewhere harder to see.
Who carries the risk when the material is wrong
The duty to stop and report is the fabricator's. The consequence is usually the buyer's.
If plate arrives undersize, with a lamination, or with a certificate that does not match the marking, the fabricator should not cut it. Doing so converts a supplier problem into a joint problem, and the buyer loses the ability to reject cleanly. A written stop notice, with photographs and a description of the discrepancy, protects both sides.
The buyer then owes a decision and a date: replace the plate, accept a deviation with a documented concession, or change the drawing. The contract should say who pays for idle time while that decision pends. Silence is expensive, because the shop redeploys the welders and the plate returns to the back of the programme.
The welding scope does not change with ownership
Buyer-supplied material is often assumed to simplify the quality scope. It does not. The welding requirement follows the product and the material group, not the invoice.
ISO 3834-2 sets out comprehensive quality requirements for fusion welding, covering procedure qualification, welder qualification, inspection and records. A procedure qualified on one steel group at one thickness range does not automatically cover another, and the fact that the buyer supplied the plate changes nothing about that. If the drawing calls for a qualified procedure and documented inspection, the same evidence is owed whether the fabricator bought the steel or the buyer did.
Free issue can raise cost here. A fabricator with a qualified procedure for its usual grades may need a new qualification for a grade the buyer happens to hold, and that cost is easy to miss.
Buyer-supplied or supplier-supplied: what actually differs
| Question | Supplier buys the steel | Buyer supplies the steel |
|---|---|---|
| Who holds the certificate | Fabricator, as part of its material control | Buyer, who must transfer it to the fabricator |
| Cutting loss | Inside the price | A separate agreement |
| Price transparency | Low, material bundled into the rate | High, labour and process visible |
| Schedule risk on material | Fabricator's | Buyer's |
| Title and insurance in transit | Fabricator until delivery | Buyer until accepted on site |
| Replacement of a wrong plate | Fabricator's problem | Buyer's problem, and the shop waits |
The right column is not automatically worse. A buyer with genuine surplus stock, a fixed grade requirement, or a client-mandated origin can save real money. It just buys a different set of obligations.
What to put in the enquiry
| Input | Why the fabricator needs it |
|---|---|
| Grade, standard and thickness, per plate | Confirms the procedure and the cutting plan |
| Certificate type required, by EN 10204 number | Fixes what evidence arrives and who signs it |
| Delivery point, date and phase | Sets storage and handling scope |
| Cutting loss allowance and offcut ownership | Prevents a variation later |
| Whether PMI or additional testing is required | Adds a receiving step and its cost |
| Who pays for replacement and idle time | Decides how a discrepancy is handled |
| Insurance and storage conditions in custody | Allocates risk while the plate sits |
The contract manufacturing service covers fabricated structures, machined interfaces and sub-assemblies made to drawing, and the material certificate guide goes further into what each document proves. Buyers comparing quotes should also read what drives the price of made to drawing parts, because free issue changes which of those drivers the buyer now controls.
Free issue steel is a legitimate way to use material a buyer already owns, provided the certificate, the loss allowance and the delivery sequence are settled before the first plate is cut. Left to the shop floor, they tend to be settled by argument.