The question that arrives after the price
A precast line is rarely one machine from one builder. It is a casting bed or a circulation system, a concrete distribution arrangement, steel moulds, a curing installation, handling equipment and a control layer that ties them together. The purchase is discussed in terms of output, layout and price. Somewhere between the purchase order and the first energised shift, somebody asks who signs the document that says the installation is safe to run.
Answering it decides who carries the risk assessment, who guards the joints between machines, and whose name is on the file an inspector will ask for.
Two legal objects, not one
European machinery law separates a machine from an assembly that is nearly a machine.
Machinery is an assembly fitted with a drive system, made of linked parts with at least one moving, joined for a specific application. Partly completed machinery is an assembly that is almost machinery, cannot perform its application on its own, and is intended only to be incorporated into, or assembled with, other machinery.
The distinction matters because the paperwork differs. Complete machinery carries a declaration of conformity and a CE mark. Partly completed machinery carries a declaration of incorporation and assembly instructions, and it is not CE marked. The Health and Safety Executive for Northern Ireland states the limit plainly: the partly completed status cannot be used to avoid conformity assessment by leaving the guards off.
A single module that can perform its own application alone is machinery in its own right, even when it later becomes part of a line. That is where line orders begin to fragment, with six machines each carrying its own declaration and an assembly that carries none.
What a declaration of incorporation says
Annex II of Directive 2006/42/EC lists the contents: the manufacturer and the person authorised to compile the technical documentation, identification of the assembly, which essential requirements are applied and fulfilled, an undertaking to transmit information to authorities on reasoned request, and a statement that the assembly must not be put into service until the final machinery into which it is to be incorporated has been declared in conformity.
Read the last clause again. It is an admission that the assembly is incomplete by design, and a transfer of the remaining obligation to whoever finishes the job.
Who becomes the manufacturer
This is the clause buyers miss. The party that assembles the line into working machinery, or puts it into service, takes on the manufacturer's obligations for that assembly: the risk assessment of the whole, guarding at the interfaces, instructions for use and the technical file.
In practice the split follows the delivery boundary:
| What the supplier delivers | Who is likely to be the assembler |
|---|---|
| A working line, commissioned, with its own control system | The line supplier |
| Machines and modules, integrated by the buyer | The buyer, or the buyer's integrator |
| A line split across two suppliers | Whoever owns the interface, written down |
Two suppliers and an unwritten interface is the configuration that produces a line nobody has declared.
The 2027 change is already inside current orders
Regulation (EU) 2023/1230 replaces the directive and applies from 20 January 2027. It keeps the partly completed machinery category and the declaration of incorporation, adds provisions for safety functions that depend on machine learning and for compliance-relevant software, and makes digital instructions the default, with paper available on request, as the European Commission's machinery pages set out.
For a line ordered now and commissioned after that date, the order should say which regime the documents will reference. A declaration written against the old directive is not wrong today, and it is not what a site inspector will ask for in 2028.
The interfaces carry the risk
Most of the residual risk in a line sits at the transfer points, the shared walkways and the control layers where one machine's stop does not reach the next.
The method is standard. ISO 12100 sets out the risk assessment and reduction process, and a whole-line assessment has to cover the interfaces that no single machine builder owned. Guards, access, restart after a stop, isolation points and the reach of an emergency stop all belong to that assessment. How the electrical and control scope is split across a supply connection is a separate order question, covered in control scope in a precast production line order.
Where the line is declared by the supplier, this work is inside their scope and should be visible in the offer. Where the buyer assembles, the same work is now the buyer's, and it is usually more than expected.
The buyer's existing plant is part of the assembly
A new line almost never lands in an empty building. There is a batching plant, an overhead crane, a loader, conveyors and a yard that were there before the order, and they connect to the new equipment at defined points.
Each of those connections is an interface, and each one pulls the buyer into the assembler's role unless the contract says otherwise. A conveyor feeding a new casting bed from an existing mixer is a joint the line supplier may not own, and the safety functions across that joint belong to whoever assembles the whole.
The practical move is a one-page interface list issued with the enquiry: every connection to existing plant, who supplies the hardware, who commissions it, and who is responsible for the risk assessment across it. Suppliers answer that list because it tells them where their scope ends. Buyers who leave it out usually discover the answer during commissioning, when the wiring is already in the tray.
What to write into the order
| Item | What to state |
|---|---|
| Delivery boundary | Which items arrive as complete machinery, which as partly completed assemblies |
| Documents | Declaration of conformity or incorporation per item, plus assembly instructions |
| Language | The language the site authority and the operators will accept |
| Assembler | Named party responsible for the whole-line assessment and declaration |
| Technical file | Who holds it, for how long, and who answers an authority request |
| Change | How a later addition is declared, and who signs it |
The declaration has to be kept for at least ten years from the last unit manufactured, which outlives most project teams. Naming a holder in the order is cheaper than reconstructing the file later.
Outside the European Union
Most line buyers are not in the EU, and the question does not disappear; it only changes its name.
What a site needs before energising is a document set its own authority, insurer or client's engineer will accept: an assessment of the assembly, guarding at the interfaces, instructions in a language the operators read, and a named party who signs. The list is nearly the same, but the label is not.
Asking a supplier for the CE documents in a market where CE has no standing produces either silence or a folder of component certificates. Asking which party declares the assembly, and in what form, gets an answer that can be written into a contract.
Where the supplier's scope usually stops
Realjet delivers precast production lines as project packages covering casting equipment, moulds and the interfaces to batching, curing and handling. The precast beam factory production line is where that scope is described in detail.
What sits outside it is the declaration itself. Which party assembles, which regime applies, whether a notified body is involved and what the local authority will accept are project decisions. They are worth settling before the order, because they decide who carries an obligation that runs for a decade.