A precast production line is bought as a set of machines but it runs as one system. The batching plant has to know when a mould is ready. The distributor has to know where the pallet is. The curing chamber has to know what is inside it. None of that happens by itself, and none of it is included in the price of any single machine unless somebody wrote it into a scope.
Mechanical gaps at handover are visible in the first week. Control gaps appear at the first attempt to run the line in automatic, which is usually after the equipment has been paid for and the commissioning team is counting days.
The point of connection is the first boundary
IEC 60204-1 covers the electrical equipment of machines that are not portable by hand, including, in its own words, a group of machines working together in a coordinated manner. Its scope begins at the point where the supply connects to the electrical equipment of the machine. Everything upstream of that point is the building installation, which is a different standard and a different contractor.
That single sentence is the most useful thing a line buyer can carry into a technical review. If the contract does not name the terminal, the cable, the isolator and the earthing point, then two suppliers will each assume the other one is providing it, and the gap will be discovered when the cabinets arrive.
One line, several control systems
A beam line of any size carries at least four separate control systems: batching and mixing, concrete transport and placing, vibration and mould handling, and curing. A circulation line adds the pallet circuit and its drives. Each of those systems normally ships with its own cabinet, its own PLC and its own software, from a different supplier, often in a different language.
Interlocking them is design work, and no single machine supplier delivers it. The signals that matter are handshakes: a permit to pour, a pallet in position, a mould closed, a chamber door available, a fault that stops upstream equipment before it makes a mess. Somebody has to own the list, and it is not the same somebody who owns the machines.
Safety functions come from a risk assessment
ISO 13849-1:2023 sets out how safety related parts of control systems are designed, and how a performance level from a to e is achieved through architecture, component reliability and diagnostic coverage. It is explicit about what it does not do: it does not specify which safety functions an application needs, or the required performance level for them.
That required level comes from a risk assessment under ISO 12100, which depends on the layout, the access routes, the frequency of intervention and the severity of what happens if a guard is opened while a vibrating table is running. The buyer and the plant designer hold those inputs. A machine supplier can build to a stated performance level. It cannot invent one.
Stop category changes the mechanics
IEC 60204-1 defines three stop categories, and the choice changes hardware rather than paperwork. Category 0 removes power immediately. Category 1 keeps power while the machine decelerates in a controlled way, then removes it. Category 2 keeps power available so an axis can hold position.
On a precast line the choice is not academic. A transfer cart carrying a half set pallet needs a controlled stop. A vibrating table may need an immediate one. A hydraulic core puller needs a defined position at stop, or the core stays in the concrete. Each of those decisions belongs in the technical annex, because they change the drives, the braking resistors and the safety relay.
The signal list is the contract
| Interface | What has to be defined | Who usually forgets it |
|---|---|---|
| Batching to casting | Call for concrete, mix type, batch complete, quantity delivered | Both sides, because each assumes a hard wired handshake |
| Casting to pallet circuit | Pallet identity and position, permit to pour, pour complete | The line integrator, when there is one |
| Mould to machine | Mould closed and locked, side form position, core withdrawn | The mould supplier and the machine supplier separately |
| Curing chamber | Chamber and slot allocation, door open, temperature and time | The curing supplier, as an option |
| Line to plant | E stop chain, fire alarm, power failure response | The buyer's electrical contractor |
| Line to office | Production count, cycle records, batch traceability | Nobody, until the buyer asks for a report |
The last two rows are where a line order turns into a software project. A hard wired E stop chain is cheap. An E stop chain that also reports to a plant system is not.
Software, passwords and the source file
A PLC program is a deliverable, and a line buyer should decide at order stage whether it is part of the purchase. Three questions settle most of it: does the buyer receive the source project file, not only the compiled program; are the passwords handed over; and who is allowed to modify the logic after handover.
The consequence shows up in maintenance. A line whose program can only be changed by the original supplier is a line with a permanent dependency, and the cost of that dependency appears years later when a small change is needed. Asking for the source file and a documented backup routine at the quotation stage costs far less than negotiating for it during a breakdown.
Interfaces also need a version. Two suppliers integrating at site should be working from a signal list with a revision number and a date, and the commissioning record should state which revision is running.
Spare inputs and the parts that stop a line
Every line ends up needing one more sensor than it was designed with, usually within the first year. A spare input and output allowance of ten to fifteen percent on each cabinet is a small cost at build stage and a large saving later. The same logic applies to spare capacity in the safety circuit and to a small stock of the sensors and relays that stop the line when they fail.
Put it in the quotation as a line item. Buyers who ask for it get a number they can compare, and buyers who do not get the supplier's default.
What the RFQ should carry
- The single line diagram and the point of connection, with the transformer, main isolator and earthing arrangement named
- Which supplier provides which cabinet, and the terminal box where responsibility changes hands
- A signal list template, so every bidder prices the same interfaces
- The risk assessment, or at least the safety functions and performance levels the buyer expects
- Stop category for each machine, stated per machine rather than per line
- Required spare input and output allowance
- Whether source code, passwords and backups are included
- The documentation set: as built drawings, cable schedules, I/O lists, manuals in the language of the plant
- Who provides site wiring, who supervises it, and who signs the loop check
- The factory acceptance test and site acceptance test protocol, including who writes it
This overlaps the utility capacity question, which is about how much power and air the plant must supply. The control question is different: it is about who owns the intelligence once the power arrives.
Where the split usually fails
Most line projects fail on the same three points, and none of them is exotic. A cabinet arrives without the interface relays, because the interface was described in a meeting rather than in a document. A commissioning team reaches site to find that the buyer's electrician has not pulled the cables between machines, so a complete line sits unconnected. A factory acceptance test exercises each machine on its own, which leaves the handshakes to be tried for the first time on the buyer's floor with production waiting.
One document prevents all three: a scope matrix that names every interface, every supplier and every test. It takes a day to write and it is worth more than the discount a buyer might negotiate instead.
Where this fits Realjet's scope
Realjet delivers precast production lines as project packages, covering casting equipment, moulds and the interfaces to batching, curing and handling. The control split, the signal list and the division of site work are settled in the technical review, and whatever is left open there becomes a variable in the price.
The equipment package scope article sets out what sits inside such a package, and the automation buying guide covers how much automation is worth paying for in the first place.