The crane is bought with the building, not with the line
On a beam line, the overhead crane is usually procured outside the equipment package. The building contract carries the runway beams, the crane arrives from a specialist supplier, and the line supplier is asked for weights and lifting points after the layout has been fixed. By then the crane capacity is often already decided by a rule of thumb, and the two numbers that matter most, the heaviest lift and the height it has to reach, are being confirmed rather than designed.
That order is worth reversing. The crane touches every mould, every cage and every finished unit on the line, and its capacity sets the hook height, which sets the building height, which sets the cost of the hall.
What the crane actually lifts on a beam line
The list is longer than the layout suggests. Side forms and end forms come off and go back on every cast. Rebar cages arrive as complete assemblies and have to be landed without racking. Prestressing strand coils and anchorages are lifted at low weight but high frequency. Finished girders leave the bed for the storage yard, and on many lines the same crane loads the truck. Mould bases, internal forms and curing covers complete the list.
Each item has its own weight, centre of gravity and tolerance for being swung. A crane sized on the finished beam alone will be asked to do most of its work at a fraction of its rating, with the slowest travel speeds and the least precise positioning, which is the opposite of what a repeated cycle needs.
Duty class comes before capacity
The classification in ISO 4301-1 is built from the total number of working cycles over the design life, the load spectrum factor and the average displacement, and the current edition uses the cycle based method rather than the older time based one. Older nameplates often carry the FEM notation instead, and the two systems are close enough to be confused in conversation and different enough to matter in a specification.
Two cranes with the same rated capacity can therefore be very different machines. A line casting several units a day, every day, with the crane working a full shift, sits in a higher duty class than the same tonnage in a maintenance bay. Buyers should state the planned cycles per shift, the number of shifts and the intended service life, and let the crane supplier return a class. If the class is decided by the buyer without that data, it is usually decided too low, because a low class is cheaper to quote.
Duty class also sets the inspection regime, and a low class shows up there as extra downtime. Under OSHA 1910.179, overhead and gantry cranes must be marked with their rated load and inspected at defined intervals, and a crane that is worked beyond its class will fail those inspections sooner.
Capacity is the heaviest single lift plus what hangs under the hook
The rated capacity has to cover the load and the gear that carries it: spreader beam, slings, lifting frame, and on some lines a vacuum or mechanical grab. A 20 t girder with a 3 t spreader is a 23 t lift, and the crane's rating applies to the hook, not to the concrete.
Two further allowances are easy to forget. The first is the heaviest mould assembly, which can exceed a short beam and is lifted as a single rigid body with no tolerance for twist. The second is any lift that has to happen at a radius or height where the crane is already derated, for example a long span where the trolley sits at the far end of the bridge.
Span, runway and the column grid
Span is set by the runway centres, and the runway centres are set by the building columns and by the working aisle the line needs. A crane that is too small in span leaves dead space along the wall. A crane that is too large forces the columns out, which changes the roof structure and the drainage.
The other dimension that gets missed is the approach: how close the hook can come to a column line, and how much side clearance the end carriage needs. On a line where a mould has to be set down within a few centimetres of a bed stop, the approach dimension decides whether the operator can place it at all, or whether every lift finishes with a bar and a shove.
Hook height over the bed
Hook height is measured from the operating floor to the hook at its highest position, and it has to clear the tallest combination the line will ever present: bed surface, mould depth, the unit, the lifting frame, the slings at their working angle, and a margin for the operator.
This is one of the few mistakes on a precast line that is hard to undo. Raising a crane runway after the building is up means new columns or new brackets, and lowering the bed is not usually an option once the foundations are poured. The hook height should be calculated from the layout drawing before the building design is frozen, and the calculation should name the unit that governs it.
One crane or two
A single crane is simpler to operate and cheaper to maintain. Two cranes allow one to work the casting beds while the other serves the yard, and on a long hall they cut travel time substantially. The second machine is not the whole cost: two cranes need a runway designed for two, an operating rule that keeps them apart, and a control system that prevents them being driven into each other.
Tandem lifts, where two cranes share a long unit, are a separate decision again. They require matched speeds, a defined load sharing arrangement and a lifting frame designed for the purpose. A line that expects to handle long girders with two cranes should say so at the enquiry stage, because the cranes then have to be supplied as a pair rather than as two independent machines.
Lifting points the line supplier has to declare
The crane supplier needs numbers that only the line supplier can give: the weight and centre of gravity of each mould assembly, the position of the lifting points, and whether the mould is designed to be lifted with the unit inside it. The same applies to the mould bases, the internal forms and any curing cover that has to be moved by crane.
Where the finished unit is lifted by cast-in inserts, the insert type and position belong to the component design, and the lifting frame is usually a separate fabricated item. That frame is a made to drawing weldment like any other, and it carries the same questions about capacity, proof load and inspection as the crane itself. A steel lifting beam made to drawing is the usual answer, and its weight has to be added to the load case.
Interfaces that decide the layout
The crane serves the curing chamber, the storage yard and the loading bay, and each of those interfaces puts a constraint back on the crane. Curing chamber doors set a maximum load width. Storage racks set a maximum stacking height and a minimum hook height above the top of the stack. Truck loading sets a reach beyond the runway, which may mean a cantilever, an additional bay or a mobile unit for the yard.
Finished beam storage and handling covers the yard side in more detail. The point for the crane enquiry is that these constraints have to be collected before the capacity is fixed, not adjusted afterwards.
What to put in the enquiry
- layout drawing with bed positions, curing chamber, storage and loading bay
- span between runway centres and the available hook height
- the heaviest single lift, with the gear that goes with it
- cycles per shift, shifts per day and intended service life
- required travel, cross travel and hoist speeds, and the positioning accuracy the line needs
- control method, and whether the crane will be operated from a cab, a pendant or radio
- power supply arrangement and the interface with the building electrical works
- which items are in the crane scope and which sit with the line or building supplier
The scope list is the item that most often goes missing. Crane, runway beam, rail, conductor bar, bumpers and the structural connection to the column are usually split across three contracts, and each supplier assumes a different boundary.
Where the boundary sits
The line supplier defines the loads, the lifting points and the sequence the crane has to serve. The crane supplier designs the machine and certifies its capacity. The building designer carries the runway and the loads into the structure. Nobody in that chain owns the fit between them unless the buyer writes it down.
Realjet delivers precast production lines as project packages covering casting equipment, moulds and the interfaces to batching, curing and handling, and states mould weights and lifting points as part of that scope. The precast beam factory page sets out what the line package includes. For the wider planning sequence, layout and RFQ checklist covers the inputs that have to be settled alongside the crane.