A breakwater armour layer is a pile of identical concrete units placed in a pattern. The units look simple, and the mould order that produces them is not, because the shape dictates how the mould opens, the mass dictates how the workshop and the yard handle it, and the placement rate dictates how many moulds exist at all.

Buyers usually arrive with the unit geometry approved and a required number of units. What sits between those two facts is a production plan, and the mould order is where it gets fixed.

What the mould order settles before the first cast

Four decisions are made at order stage and are expensive to revisit later: the number of mould sets, the way each mould opens, the casting orientation, and the handling interfaces.

All four are connected. A mould that opens by hand needs panels light enough for two people, which limits unit size. A mould that opens with a crane needs lifting points and a yard crane with the reach and capacity to serve every mould position. A mould that opens hydraulically needs power, controls and the safety measures that come with powered movement.

Getting the order wrong usually shows up as a rate problem rather than a quality problem. The units come out correct and too slowly, and the pour programme slips week by week.

Unit mass sizes the whole yard

The first number to fix is the mass of a single unit, because everything downstream is sized by it.

A unit of 8 t at a concrete density of about 2.4 t per cubic metre occupies roughly 3.3 m³, which is a shape about 1.5 m across in each direction. That is small enough to lift with a mid-size yard crane and large enough that two people will not be moving it.

Mass also sets the comparison with rock. Concrete armour units are used where the required rock size cannot be supplied, and published case work on single layer systems describes toe armour needing 8 to 12 t rock where supply became the constraint, with concrete units adopted instead in a Colombo South Harbour breakwater case study. When a project moves to concrete units, the mass range is normally set by the design, and the mould order has to work inside it rather than average across it.

The handling consequences are concrete:

  • The yard crane must lift the unit, the lifting frame and any mould panel it serves, at the radius of the furthest mould position.
  • Each unit needs a lifting point or sling arrangement cast in or fixed to the mould, and the location has to suit the unit's centre of gravity, which for an interlocking shape is not the geometric centre.
  • Storage and curing space is proportional to unit footprint times the number of units in the yard, and units cannot be stacked arbitrarily because the interlocking faces damage each other.

Mould count follows the casting cycle

The number of moulds is not a round number chosen for convenience. It comes out of the required output and the cycle time.

Take a project needing 60 units a day at peak. If a unit stays in its mould for a full day before stripping, then 60 mould positions are needed to sustain that rate, because each position produces one unit per day and no more. If the concrete mix and the curing regime allow stripping sooner, the same 60 units can come from fewer moulds, but only if the mould can be cleaned, oiled, re-assembled and re-filled inside the shorter window, which is where labour becomes the constraint.

Three planning figures usually decide the answer:

Figure Where it comes from Effect on the order
Units per day at peak Placement programme divided by working days Sets the minimum mould count
Hours in mould Mix design, ambient conditions, curing method Sets how many casts each mould can make
Stripping strength Project specification for the unit Sets the earliest safe demould

A buyer who doubles the mould count without checking the stripping requirement buys storage and handling, not output. A buyer who reduces it below the cycle requirement buys a slower programme.

Segmentation for an interlocking shape

An armour unit is not a box. Its faces interlock, which means the mould cannot simply lift off: at least one face has to move outward, and usually more than one.

The segmentation follows the geometry. Panels are arranged so that each one can be withdrawn without dragging across a re-entrant corner, and the joint faces are machined or fitted so the assembly closes to the same position every time. A joint that closes 2 mm differently between casts produces units that do not sit together on the slope, and the placement crew discovers it at the water's edge.

The opening method then follows the panel mass. Realjet's steel moulds for interlocking armour units are reviewed in three configurations: manual opening where unit size and lifting equipment allow direct panel handling, lifting-assisted opening where panels need crane support, and mechanically or hydraulically assisted opening where repeated movement justifies powered assistance.

Where powered opening is specified, the safety measures are not optional. ISO 12100 sets the general principles for machinery risk assessment and risk reduction, and a mould with hydraulic rams, a power pack and a control station is machinery in that sense, even though it spends its life full of concrete.

Casting orientation and the concrete face

The second decision that hides in the order is which face is cast down. That face takes the mould surface finish, holds the air, and determines where vibration can reach the concrete.

For an interlocking unit the down face is usually a flat or near-flat panel, and the up face carries the features that interlock. Casting in the other orientation produces a different surface quality on the visible faces of the armour layer, which matters on a structure inspected by the client and less on a submerged toe.

Vibration access is the practical constraint. A deep, narrow mould with internal features cannot be reached by a poker from the top in every position, so the mould arrangement has to leave access, or the concrete has to be placed in lifts with external vibration. The mix design and the mould design are therefore agreed together, not sequentially. Buyers comparing precast concrete mould types usually find that the casting orientation is what distinguishes one supplier's proposal from another.

Yard layout: curing, storage and crane reach

The moulds are only part of the footprint. Each mould needs a casting position, a stripping position, a curing area and a storage slot, and the four are rarely the same place.

A workable arrangement puts the moulds in a row served by a crane runway, with stripping and turning at one end and storage beyond it. Units cure in the storage row while the moulds keep turning, so the yard holds several days of production at any time. Sixty units a day at 3 m² each is 180 m² of new storage every day, which is the number that catches out buyers who planned the moulds and not the yard.

Ground bearing is the other half. A cured 8 t unit on a small footprint imposes a point load that a slab designed for a forklift may not take, and settlement under a stack shows up as cracked units.

Concrete, stripping and the first unit

The specification that governs the units also governs the mould, because a mould that cannot survive the stripping method will not produce the programme.

Three items should be stated in the order, in writing:

  • The stripping strength at which the mould may be opened, taken from the project specification rather than assumed.
  • The surface finish required on the faces that will be visible in the completed structure.
  • Whether a trial unit is required before series production, and who attends.

A trial unit is cheap insurance. It proves the opening sequence, the lifting arrangement, the finish and the dimensional check in one cycle, and it gives the client something to accept before sixty units a day start arriving. The same logic applies to the workshop trial assembly of the mould, which is where joint closure and panel alignment are proved.

Licensing and unit naming

Many interlocking armour systems are proprietary, and the geometry is licensed rather than public. That affects a mould order in a specific way: the mould maker works to the geometry the client is licensed to use, and the client is responsible for the licence and for the naming used in project documents.

A supplier describing a mould type generically is not granting a licence, and an order should not read as if it were. The definition of an interlocking armour unit mould covers that boundary, and it is worth settling before drawings are exchanged.

What to put in the enquiry

Input Why it is needed
Approved unit geometry and mass Sizes the mould, the panels and the handling
Required units per day, and the peak week Sets the mould count
Stripping strength and curing method Sets the cycle, and whether steam or ambient curing is planned
Casting orientation Sets the mould surface, the air path and the vibration access
Opening preference Manual, lifting-assisted or powered, with the crane capacity available
Yard crane capacity and reach Rules out configurations that cannot be served
Storage area available Tests whether the mould count and the yard agree
Surface finish and trial unit requirement Defines acceptance before series production
Licence and naming position Keeps the order and the project documents consistent

The marine and coastal mould range covers armour units, caissons and similar structures, and the enquiry route through the mould catalogue starts from the unit, not from a product name.

Settle the unit mass, the casting cycle and the yard space before the panels are detailed. Those three decide whether the mould supports the placement programme or paces it.