A steel armour unit mould can look complete in a workshop photograph and still arrive with panels that need forcing into position. Trial assembly is the point where the buyer can see whether the mould closes, holds its geometry and opens again without damage. It is a purchase check. First cast approval still happens on the production line.

Realjet supplies project specific steel moulds through its precast concrete moulds range. For four leg armour units, the geometry belongs to the project designer. If the unit name or shape is controlled by a proprietary system, the buyer supplies the approved geometry and confirms the right to use it. The mould maker works to that information and states what is included in the workshop assembly.

What a trial assembly should prove

The trial should answer three questions. Do the panels fit together with the specified fasteners? Does the closed cavity match the approved geometry within the agreed tolerances? Can the mould be opened in the stated sequence without striking the cast unit? A successful assembly covers all three. A photograph of the closed mould only covers the first.

For a marine and coastal mould order, the trial also checks the details that are easy to lose between projects: hinge position, joint line, lifting lug location and base frame interface. These items affect how the mould behaves on a casting line, even when the unit geometry is unchanged.

Start from the approved drawing

The acceptance drawing must be named in the order. It should show the unit geometry, the mould split, the datum references and the dimensions that matter for fit. ISO 1101 provides the geometrical product specification language for those references. Using that language avoids a drawing note that means one thing to the designer and another to the fabricator.

Where the buyer supplies a physical master or reference unit, say which one is authoritative and how it will be protected during the trial. If the drawing and the master disagree, the contract should state which document wins. That decision belongs to the buyer, because only the buyer can approve the project geometry.

Check panel fit before measuring the unit

Start with the parts that join. Bolts should pass through holes without being drawn into place by thread force. Hinge pins should line up across the full length of the hinge. Joint faces should meet without a step that will print onto the concrete. Any shim used to make a panel fit should be recorded, because it becomes part of the delivered mould rather than a temporary workshop fix.

A panel that needs heat or force to assemble is a warning sign. It may still produce a unit on the first cast, but repeated opening and closing will make the problem worse. The trial is the place to find it before transport.

Record any dowel pins used to repeat a position. Dowels that are a tight fit in one panel and loose in the mating panel allow the cavity to shift each time the mould is assembled. Note the fit in the trial record and agree whether the pins are part of the spares package. A buyer who receives one pin and no replacement will learn about that during a mould changeover on the line.

Measure the cavity, not only the outer frame

Overall mould size is easy to measure and easy to misinterpret. What matters is the cavity that forms the unit: leg angles, leg length, central body and the transition between them. Record the measuring equipment and the temperature, since large steel panels move with shop temperature. Where a project uses a coordinate measuring machine or a laser tracker, state that in the order and agree the report format.

The mould tolerance guide explains which dimensions buyers usually control. For armour units, add the dimensions that govern stacking and interlock, even when they are not shown as structural tolerances on the unit drawing.

Verify the opening sequence

A multi part mould only works if the panels can be removed in the order the operator expects. During the trial, open the mould as if a cast unit were inside. Watch for panels that must pass through the space occupied by the unit, hinges that foul the base frame and loose parts that can be dropped into the cavity.

The opening sequence should then be written into the instruction sheet and marked on the mould where practical. If the line operator has to guess which panel comes off first, damage is likely during the second or third cast. Include that information in the delivery.

Lifting and handling interfaces

Trial assembly is also the moment to check lifting lugs, tie down points and the space a crane hook needs. A mould that assembles correctly but cannot be turned for cleaning is a production problem. Check that each lug is accessible with the mould fully assembled and that slings do not bear on hinge covers or joint bolts.

The mould weight and lifting points guide covers the information a buyer should send before design starts. Add the site crane arrangement to the trial plan, because a mould that fits the workshop trolley may not suit the line crane.

Weld and surface condition at the trial stage

During trial assembly the mould may be unpainted or partly painted. That is useful, because welds and grind marks are easier to see. ISO 5817 defines quality levels for imperfections in welded joints and gives the parties a common reference when a weld appearance is disputed. Agree the applicable level in the order rather than expecting every weld to meet an architectural finish.

Realjet's welding quality system is certified to ISO 3834-2. That supports process control, but it does not replace the buyer's acceptance criteria for surface finish or dimensions. The trial record should separate what was inspected as fabrication quality from what was measured against the unit drawing.

What the buyer should witness

A buyer may attend in person or appoint an inspector. State which option applies and give enough notice for the mould to be assembled at the agreed stage. The inspection should include panel fit, dimensions, opening sequence, lifting points, fasteners and marking. Record the names of the people present and the serial numbers of the mould parts.

A witnessed trial does not transfer responsibility for the concrete unit to the buyer. It confirms that the mould met the agreed workshop checks at that date. If the mould is later modified, the record must be updated or the modification must be accepted under a new agreement.

Packing and reassembly instructions

Disassembly for transport can undo the work done at the trial. Ask for each panel to be marked so it can be reassembled in the same order. Bolts, dowels and hinge pins should be bagged and identified by station. The packing list should match the trial record, so a missing shim or special bolt is visible before the crate leaves the workshop.

If the mould travels in more than one package, state which panels must arrive first. On a precast production line, the installation crew may need to build the base before the upper panels can be set. A clear packing sequence reduces time spent on site and avoids trial and error with heavy parts.

Contract boundaries and sign off

The supplier owns fabrication, workshop assembly and the records it can produce. The buyer owns the approved geometry, proprietary naming rights and the acceptance criteria. The project designer owns the unit geometry and any change to it. Where a first cast is required, the order should say how it relates to the workshop trial and who approves the result.

A short checklist in the RFQ is enough to start: approved drawing, datum scheme, measurements to take, opening sequence, lifting check, weld reference, witnesses and record format. With those items fixed, a trial assembly requirement can be priced as part of the mould order instead of negotiated after manufacture.