A welded frame can pass dimensional check, pass visual inspection, and still fail ultrasonic testing on one butt joint. Rejection is an ordinary event in fabrication. What separates a well run order from a difficult one is whether the paperwork already says who approves the repair, how the defect is removed, what gets re-tested, and who carries the cost of the second inspection.

Most enquiries leave that blank. A drawing pack will state a weld quality level and an execution class, and then stop. The repair clause is often one line in general terms, or nothing at all. When a defect appears three weeks into the order, both sides negotiate from memory, and the schedule absorbs the argument.

Where a repair sits in the sequence

Three responses are available when a weld does not meet acceptance: repair it, rework the part, or replace the component. Repair means removing the defective metal and depositing new weld in the same joint. Rework usually means cutting, re-fitting, or re-machining something that was built outside tolerance. Replacement means starting the part again.

The three have very different consequences. A repair on a frame that is still in the bay costs welding time and re-inspection. The same defect found after machining, after galvanizing, or after the frame has been trial assembled costs machining time, a second trip through the coating line, or a second trial assembly. The earlier the repair rule is agreed, the more of that cost stays visible before it is spent.

A repair is welding, so it needs a welding procedure

Repair weld metal is not exempt from the quality system that governs the original weld. A fabricator working to ISO 3834-2 applies the same control to a repair as to production welding: an approved procedure, a qualified welder, the specified consumables, and a record.

The procedure itself is normally covered by the same qualification as the original joint, which is what ISO 15614-1 governs. Repairs that change the essential variables, such as a thicker section, a different position, or a preheat that the original procedure did not cover, need their own support. That is worth settling at enquiry stage if the part has thick sections or restricted access, because a repair procedure that has to be qualified from scratch is a schedule item, not a formality.

Welding procedure and NDT records explains what a buyer should expect to see before production starts. The repair question is the same evidence, applied after a rejection.

Removing the defect before anything is deposited

The step that decides whether a repair works is removal. Defective metal has to come out completely, and the excavation has to be smooth enough to weld into. Gouging and grinding are the usual methods, and both leave a surface that needs cleaning before the arc is struck.

United States federal welding specifications handle this in plain language. The structural welding guide specification UFGS 05 05 23.16, section 3.5, requires corrections to follow AWS D1.1 and states that after a defect is thought to have been removed, and before re-welding, the area is examined by suitable methods to confirm the defect has gone. It also requires defects found between passes to be repaired before more weld metal is added.

Skipping that confirmation is how a repair turns into a second rejection. A crater ground back by eye and welded over will pass a visual check and fail the same ultrasonic test as before, and the part then carries two thermal cycles instead of one.

What has to be re-tested

The same specification is direct about the evidence: repaired welds must meet the inspection requirements for the original welds. Not a visual check in place of the original ultrasonic test, and not a sample of the repaired area. The method that found the defect is the method that clears it.

In practice the retest scope should be written in the order as three items: the method, the extent, and the acceptance level. A repair in a butt weld that was examined by ultrasonic testing is re-examined by ultrasonic testing over the repaired length plus the affected heat treated zone. Acceptance after repair follows the same quality level as the original joint, which for most structural work means the acceptance levels in ISO 5817 as called up by the drawing.

Where the buyer's specification is silent, the fabricator's own quality plan fills the gap, and the two documents rarely match. This is the sort of thing that surfaces in a first article inspection rather than in a review meeting.

How many repairs at the same place

Repeated repair at one location accumulates heat input in a small volume and drives hardness and distortion in ways the original procedure never considered. Most fabricators therefore work to an internal limit, often stated as a number of attempts at the same location before the part is cut out and replaced.

There is no universal number to quote in a purchase order. What matters is that the order states one, or asks the fabricator to state one, and that the escalation path is agreed: who decides between a third attempt and replacement, and who pays for the difference. A frame with a repair history is also harder to assure later, because the record now includes a region with two or three thermal cycles and a heat affected zone that no longer matches the qualified procedure.

What a repair does to the rest of the part

Repair welding shrinks metal, and on a long frame the shrinkage from a localized repair can pull a machined pad out of flat or shift a bolted interface. Repair sequencing therefore matters on parts that are machined after welding. Distortion control covers the general problem; the repair version is that a late repair can undo work already signed off.

Coating is the second effect. A repair after galvanizing means the zinc is removed locally, the area is welded, and the coating is reinstated. That repair to the coating is a separate operation with its own acceptance, and it is worth agreeing in advance whether it is acceptable on a visible face. Hot dip galvanizing sets out what the drawing has to carry for the original dip; the repair case adds a second question about who reinstates it and how it is inspected.

What to write into the order

Item What the order should state Why it matters
Approval Who authorises a repair, and whether prior approval is needed for any repair or only above a size Prevents a repair being discovered at final inspection
Procedure That repair welding follows a qualified procedure and a qualified welder Keeps the repair inside the quality system
Retest Method, extent and acceptance level for the repaired area Removes the argument about whether a visual check is enough
Records That repair location, method, procedure reference and retest result are recorded and handed over Makes the as-built record match the part
Cost Who carries repair, retest and any consequential re-machining or re-coating Prevents the claim being settled by whoever is under pressure
Limit The number of attempts allowed at one location, and what happens after that Forces the replacement decision into the open

Cost is the line most often left out. A repair discovered before dispatch is a welding cost. The same repair found after trial assembly is a welding cost plus a second trial assembly, and on an export order it can also be a packing and shipping delay. None of that is unreasonable to allocate in advance, and all of it is difficult to allocate after the fact.

What Realjet can be held to

Realjet fabricates welded frames, structures and equipment supports to customer drawings, with machining of interfaces after fabrication. Welding is controlled to ISO 3834-2, with EN 15085-2 CL1 coverage for railway work, and includes robotic arc and GMAW welding with post-weld cleaning. Drilling, boring, deburring and sub-assembly are part of the same scope.

What the drawing and the purchase order say about repair, retest and records is agreed during technical review, and the delivery boundary is confirmed in the quotation. The contract manufacturing page sets out the service scope; the repair clause is one of the items that has to be settled before the order is placed, not after the first rejection.