The mix is settled before the machine is chosen

A precast production line is bought to cast a product from a concrete that someone else has designed. That sentence sounds obvious, and it is where a lot of arguments start, because the equipment enquiry and the mix design often run in parallel and neither side knows what the other has assumed.

The consequences are practical. A placing system sized for a 100 mm slump struggles with a mix supplied at 200 mm. A vibration system tuned for a stiff dry cast mix is not the same machine as one specified for self-compacting concrete. A curing regime that assumes a 12 hour turnover meets a mix that needs 18.

Neither purchase is at fault. The input is missing, and it belongs in the line enquiry before the quotation is priced.

Three duties that the concrete standard separates

EN 206 sets out who does what. The specifier is responsible for the specification of concrete. The producer is responsible for conformity and production control. The user is responsible for placing the concrete in the structure.

In a ready-mix supply chain those are three companies, and the split is clear enough. In a precast plant they can collapse into one organisation: the same company specifies the mix, produces it in its own batching plant and places it in its own moulds. The standard acknowledges that case directly, and notes that the specifier, producer and user may be the same party.

Owning all three roles does not remove the decisions. It removes the contract that would have forced someone to write them down. For a line purchase, that is the risk: the buyer assumes the mix is settled because it is internal, and the equipment supplier assumes the opposite.

The Concrete Society's summary of the British companion standard makes the same division: BS 8500-1 is written for the person establishing the specification, BS 8500-2 for the producer who has to meet it. Responsibility for demonstrating conformity sits with the concrete supplier, which in a precast plant means the plant's own quality control.

What the line supplier has to be told

An equipment supplier can only size a plant against a defined mix envelope. The list below is the minimum, and every item changes at least one machine.

Mix property What it changes on the line
Strength class and cement content mixer size, cycle time, heat of hydration, curing
Exposure class and water/cement ratio curing regime, steam or insulation demand
Consistence class or slump placing method, vibrator type, mould filling sequence
Maximum aggregate size hopper and pipe openings, vibrator spacing, cover limits
Self-compacting or not gate design, vibration, form pressure on the mould
Admixtures and set time working window, finishing time, stripping time
Density and yield batching accuracy, pallet and crane loads
Delivery method, plant or truck buffer capacity, receiving hopper, transfer route

A buyer who sends this table with the enquiry gets proposals that can be compared. A buyer who sends a product drawing and a target output gets proposals that each assume a different concrete, and the difference only surfaces at commissioning.

Consistence is the number that sizes the plant

Of all the properties, consistence moves the most equipment. A stiff mix needs more vibration, and it has to be moved, placed and compacted inside a short window before it stiffens.

Public specifications show the range that real precast work covers. The FHWA sample specification for precast bridge elements sets an allowable slump of 5 to 10 inches, which is 125 to 250 mm, together with a maximum water/cement ratio of 0.42, air entrainment between 5.5 and 7.5 per cent, and limits on cement and total cementitious content. The same document requires self-consolidating concrete to be trial batched to establish its properties, and states that the amount of vibration and the depth of lift for SCC are to be fixed during that trial with input from the supplier and the contractor.

That is a wide envelope. A line specified around a 150 mm slump mix and then fed at 240 mm will show it in form pressure, in segregation at the ends of a long bed, and in the finish. The mould and the placing system have to be bought for the mix that will actually arrive.

Trial batches, and the evidence they leave behind

The usual route is a trial batch before production. The FHWA sample specification requires new mix designs to be qualified by trial batches prepared to AASHTO T126, which is the same test as ASTM C192, and requires the test specimens to be cured in the same way as production if accelerated curing will be used. It also says plainly that approval of a mix design does not relieve the contractor of the responsibility of meeting the specification during production.

Two things follow for the line buyer. First, the trial batch is the moment when the mix and the machine meet, and it is worth running on the actual equipment, or at least on equipment with the same placing and vibration principle. A trial in a laboratory mixer proves the mix. It does not prove the line.

Second, the records from that trial become the reference for every later dispute about surface finish, strength or cycle time. The mix design number, the batch weights, the slump and air results, the casting temperature and the curing record are the documents that decide whether a rejected element was a mix problem or a machine problem.

Aggregate size against the section and the steel

Maximum aggregate size is often left to the concrete supplier because it is a mix decision. It is also a mould and equipment decision.

Coarse aggregate has to pass between reinforcement bars and through the gap between the steel and the mould face. Where cover is 30 mm and the bar spacing is tight, a 25 mm aggregate may not fit the space it has to flow through, and the result is a void that appears after stripping, at the bottom of a face, where it is expensive to repair.

The same number sets the openings upstream: the receiving hopper, the transfer pipe on a pump, the gate on a bucket, the spacing of external vibrators. A buyer who fixes the aggregate size in the enquiry, and states the minimum cover and the tightest bar spacing from the product drawings, gives the supplier enough to check the flow path rather than assume it.

Where the mix meets the machine

Four interfaces carry most of the risk.

The batching plant has to weigh the constituents the mix design names, including additions and admixtures, to the accuracy the specification requires. A mix with silica fume, fly ash and two admixtures needs more silos and more dosing lines than a plain mix, and the batching plant is part of the line package interface.

Placing is a choice between bucket, pump, conveyor and distributor, and they are not interchangeable. Each handles a different consistence range and imposes a different minimum opening and discharge height.

Vibration can be internal, external or from a table, depending on section shape and on how stiff the mix is. Self-compacting concrete changes the requirement, and the mould design changes with it, because a flowing mix pushes harder on the form.

The curing system is sized by the heat the mix generates and the temperature it must be held at. A mix with high cement content generates more heat and needs less steam, and a mix with a slow setter needs a longer window before stripping.

When the mix changes after the order

Mix designs get substituted. A cement source changes, a fly ash becomes unavailable, an admixture is reformulated, or a ready-mix plant supplies part of the demand during a peak. Caltrans requires a mix design submittal and a quality control plan for precast work, and treats changes to materials as a trigger for a new submittal. That is the right instinct for a line order too.

The line side of the question is what a substitution does to output. A slower setting mix lengthens the stripping time, which lengthens the pallet cycle, which either reduces output or requires more pallets. A mix with higher paste content changes the surface and the amount of cleaning between casts. A mix that needs more vibration slows the casting station.

None of that is a reason to freeze the mix forever. It is a reason to state, in the order, which mix properties the equipment has been sized for, and to agree who pays when the envelope moves.

What to put in the enquiry

  • the mix design reference, or the full set of properties if the design is not yet done
  • consistence class or slump range at the point of discharge, with the tolerance
  • maximum aggregate size, and the minimum cover and tightest bar spacing from the product drawings
  • whether self-compacting concrete is intended, and for which products
  • cement type and content, additions and admixture families
  • casting temperature range, and the curing regime intended
  • the trial batch plan, and which party witnesses it
  • the change control route for material substitution after the order

Who owns which decision

The producer owns the mix design and the conformity of the concrete. The designer of the product owns cover, bar spacing and the exposure class the product must meet. The line supplier owns the equipment that can handle the declared mix and the interfaces to batching, placing, curing and handling, and it should state the envelope its equipment was sized for.

Realjet delivers precast production lines as project packages covering casting equipment, moulds and the interfaces to batching, curing and handling. Concrete mix design, trial mix testing and product design remain with the producer and its designer. Where the mix envelope is not yet fixed, the workable route is to declare a range, price against the range, and confirm the final mix before the equipment drawing is released.

Where to take the question

The precast beam factory line describes how a production line is configured, and the precast concrete plant solution covers the wider plant scope. Self-consolidating concrete on a production line deals with the flowing mixes, concrete testing scope in a line order covers the specimens and records, and vibration and compaction covers the machine side of the same decision.