A double tee looks like a simple shape: a wide flange carried on two tapered stems. Buyers assume the mould is equally simple, then discover the order is for a set of modules that has to be set out along a prestressing bed, with bulkheads between them and an abutment at each end.

The order therefore has less to do with the shape than with the bed. Get the bed, the module count and the strand pattern agreed first, and the mould detailing becomes routine.

A double tee mould is a bed layout, not a box

Double tees are produced on long line beds. The Canadian Precast Prestressed Concrete Institute describes beds of 100 to 150 m for double tee production, with bulkheads placed to form the required slab length for each project, and the National Precast Concrete Association describes beds from 200 to 500 ft in North American practice.

That single fact changes the purchase. The mould supplies the soffit and the two stem forms, and it repeats along the bed. Between repeats sit bulkheads that close the ends of each slab. At each end of the bed sits an abutment that carries the tensioned strand.

A buyer who asks for "a double tee mould" without stating the bed will receive a quotation for an undefined number of modules, or for a single module that cannot meet the required output. The quantity is a layout decision, not a catalogue choice.

Flange width decides the module

The nominal flange width is the first number to fix, because it sets the module width and the transport envelope at the same time.

CPCI lists modular widths typically at 2400 mm, 3000 mm and 3660 mm nominal. Those are nominal figures: the actual cast width accounts for the joint gap and the edge detail, so the mould dimension is not the same as the nominal width and should not be ordered as if it were.

Two constraints sit on that number. The bed width limits how many modules fit side by side, and the road limits how wide the finished slab can travel. A plant that casts three modules across a bed gains output but has to load and permit every slab afterwards. In many markets the transport limit binds first, which is why 2400 mm remains common even where wider beds exist.

Stem depth and stem width follow the design

CPCI gives slab depths from 500 mm to 1000 mm, with stem widths sized to suit structural and fire rating requirements. That range hides most of the mould risk.

Stem width is not a constant. It changes with the load, the fire period and the amount of prestressing, and every change alters the internal form that creates the stem. A mould built for one stem width produces one family of sections. If the plant expects to sell two families, the order should say so, because the modules are not adjustable in the way that a wall panel mould is.

Depth matters for the same reason. A deeper stem needs a taller internal form, more concrete in the stem, and a different vibration approach. Ask the designer to fix the section range before the mould is detailed, not after.

The strand pattern belongs to the bed

The prestressing strand is not held by the mould. It runs from abutment to abutment, through the length of the bed, and the mould sits over it.

This is the interface that causes the most confusion in enquiries. The buyer's designer owns the strand pattern: how many strands, at what spacing, at what height in the stem, and which ones are debonded near the ends. The line supplier owns the bed and the abutment. The mould maker owns the openings that let the strand pass and the end detail that closes around it.

If the strand pattern is not fixed when the mould is ordered, the end forms will be designed against an assumption, and a later change becomes a set of new end plates rather than a drawing revision. Any debonding sleeve or strand deflector sits in this same zone, so state it early.

Bulkheads and the length range

One bed, many lengths. That is the commercial logic of a long line, and it depends entirely on bulkheads.

The slab length is set by moving a bulkhead to the required position, so the mould order should state the length range and the increments, not a single length. It should also state how the bulkhead is fixed and sealed, because a bulkhead that leaks grout at the soffit produces a ragged end that has to be cut back.

Setting out marks belong on the bed or on the side forms, not on loose drawings. A plant that casts five lengths from one bed will reposition bulkheads several times a week, and the marks are what keeps the lengths right.

Flange edges, joints and the visible soffit

The underside of a double tee is usually the finished ceiling, which makes the soffit the face that matters. CPCI notes that the slabs are cast on smooth steel forms and that the underside can be specified to standard grade, Finish Grade B or Finish Grade A as described in CSA A23.4. The mould surface is what delivers that grade, so the finish requirement belongs in the mould specification rather than in a general note on the element drawing.

The longitudinal edges deserve the same attention. Adjacent slabs form a joint, and the edge profile decides how that joint is sealed. A chamfer or a formed rebate is a mould feature; it is not something the contractor can add later. Agree the profile with the designer and put it on the mould drawing.

Demoulding and lifting

A double tee is stripped by lifting it off the soffit, which means the mould has to release cleanly across a large contact area, and the lifting points have to be where the element can take the load.

The mould design has to leave access for release, whether that is pry points at the edge, a vacuum lifter, or a lifting frame that picks up cast-in anchors. Stem side forms usually hinge or lift away before the element moves.

Where the mould carries powered movement, such as hydraulic side forms on a large module, the safety measures follow machinery principles: ISO 12100 sets out the general approach to risk assessment and risk reduction, and a form that closes under power is machinery in that sense.

What tolerance to ask for

Camber is not a mould tolerance. It comes from the prestressing and the concrete, and no mould can hold it.

The tolerances that belong in the mould order are geometric: module length, flange width, stem position relative to the flange edge, straightness along the bed, squareness of the ends, and the fit between adjacent modules. The tolerance discussion for a production line order covers how those figures are usually structured and where they get confused with element tolerances.

A module joint that steps by a few millimetres shows up as a line on the ceiling every time. That is a mould tolerance, and it is worth a specific number in the specification rather than a reference to a general standard.

What to put in the enquiry

Input Why the mould order needs it
Nominal flange width, and the cast width you expect Sets module width and the joint gap
Section depth and stem width range Sizes the internal forms and rules out later families
Strand pattern, including debonding Fixes the end detail and the openings
Bed length and abutment positions Sets module count and end form design
Length range and increments Defines bulkhead positions and fixing
Soffit finish grade and edge profile Defines the mould surface and the joint detail
Lifting method and cast-in items Sets access for release and anchor positions
Required output per shift Tests whether the module count supports it

The catalogue is organised in three levels. The range of precast concrete moulds explains how mould families are grouped, the building component moulds category covers slabs, panels, columns and stairs, and the page for steel moulds for double tee slabs sets out the configuration inputs for this product. The double tee production line overview covers the process around the mould for buyers planning a new line.

Fix the bed, the section range and the strand pattern before the modules are detailed. Those three decisions decide what the mould can produce, and none of them can be recovered by better workmanship in the workshop.