An IP code on an enclosure drawing is a test result, not a property that transfers automatically from one cabinet to the next. Two boxes that look alike can behave differently once a door is cut, a gland is fitted and a latch is adjusted. For buyers placing a made-to-drawing order, the work is to define which code applies, which parts of the enclosure are included and what evidence will be accepted.

Realjet's contract manufacturing service covers sheet metal enclosures, cabinets and welded frames built to customer drawings. The rating itself is a system requirement that the buyer sets and the order verifies. This guide follows the questions that should be settled before an enclosure fabrication quote is compared on price alone.

What the IP code actually describes

The IEC ingress protection guide defines the two numerals in the IP code. The first covers protection against solid objects and dust, from 0 with no protection to 6 with no dust ingress. The second covers water, from 0 to 9, where 9 refers to high pressure hot water from different angles. IEC also makes a distinction that matters in a purchase: the code records how a product was tested, not the conditions in which it can be used. IEC says this directly in its explanation of IP ratings.

That distinction changes the RFQ. A buyer who needs a cabinet to survive a hose down in a wash bay should say so, including water pressure, direction and duration. A buyer who needs to keep dust out of a drive cabinet should describe the dust and the cleaning method. The target code is a shorthand for those conditions, not a substitute for describing them.

Start with the installation, not the catalogue

Outdoor location, indoor wash down, dust and chemical exposure all lead to different choices. A code selected because it appears on a previous purchase may describe a different installation. Write down where the enclosure sits, who accesses it and what happens around it during a normal shift.

Then decide which parts of the assembly are inside the rated boundary. A door and body are only part of the story. Cable entries, vent pads, display windows, door switches and conduit plates all cross the boundary. If the drawing shows a target code but leaves these items open, each supplier will make an assumption, and the lowest quote will usually reflect the weakest one.

Gasket material and compression

The gasket is a purchased part with a job to do over a temperature range. EPDM, silicone and other elastomers behave differently under heat, sunlight and cleaning agents. The selection should follow the site conditions and the cleaning chemical, not the colour of the door.

Compression matters as much as material. A gasket that is too soft or too thick can be crushed at the latch points and lift at the corners. A gasket that is too hard needs more latch force than a thin sheet-metal door can carry without distortion. Specify the gasket section, its hardness where known and the permitted gap at the door edge. Ask the supplier to show how the corner joint is made, because a butt joint at a corner is a common leak path.

Ask whether the order includes a spare gasket set and who cuts the lengths. A gasket cut on site from the wrong roll can undo a verified door. If the cabinet is part of a fleet, a common gasket section across several door sizes reduces the number of spares a buyer must hold. State that plainly in the bill of materials so it is not left to the workshop.

Door geometry, hinges and latches

A flat door on a stiff flange compresses a seal evenly. A large door with widely spaced latches tends to bow between them. That bow is where water finds a way in. The order should fix the flange width, the corner radius and the latch positions, along with the hinge type and the number of hinges for a given door height.

For removable panels, the bolt pattern and tightening sequence belong on the assembly drawing. If a maintenance team is expected to open the cabinet and close it again, the design should allow the gasket to be replaced without welding or repainting. That requirement is easier to write into the order than to add after the first site visit.

Cable glands, connectors and blank openings

Most enclosure leaks happen where cables enter. A gland that suits one cable diameter does not seal a smaller one, and a blanking plug that was never fitted leaves an open hole. List every entry on the drawing with its cable size, gland type and intended location. Identify unused holes that must be closed with certified plugs rather than tape or sealant.

Decide whether glands are supplied, fitted and tested by the enclosure fabricator or by the electrical integrator. Both arrangements work, but the boundary must be written down. If the fabricator drills and threads the plate while the integrator fits the glands later, the fabricator cannot be responsible for the final rating.

Displays, vents and the sealing conflict

A door with a display window introduces a frame, a transparent panel and another set of fasteners. A vent introduces louvres or a filter, each with its own protection behaviour. Neither item can be treated as a plain sheet-metal cutout. Where cooling is needed, the buyer should define the airflow and let the designer choose between a sealed heat path and a filtered opening. Mixing the two on one door usually produces a drawing that is hard to price and harder to verify.

Surface finish also affects the seal line. Powder coating builds thickness at the flange, and masking may be needed where the gasket lands. The surface treatment RFQ guide explains how coating scope is separated from fabrication scope. Put the masking requirement on the same drawing as the gasket, not in a separate email.

Drawing content the fabricator needs

A useful enquiry package contains the overall size, door and panel layout, material and thickness, finish, gasket and latch details, entry schedule and the target code. It should also state which standard defines that code and which edition is intended. A model is helpful, but a dimensioned drawing is what a fabricator can quote and inspect against.

For buyers preparing a package, the drawing and BOM readiness guide sets out the information that removes guesswork. Mark any dimensions that are critical to sealing, such as flange flatness and door gap. Mark the interfaces that belong to another supplier, such as internal electrical panels or cable terminations.

Test evidence and acceptance records

Ask what will be done to verify the rating and who will sign the record. A supplier declaration may be enough for a non critical cabinet. A project specification may require a test report from a named laboratory or a witnessed test on a sample door. The answer changes cost and lead time, so it belongs in the enquiry rather than in a later discussion.

An inspection and test plan can list the checks before dispatch: dimensions, coating thickness, gasket presence, latch operation and any ingress test. Records should identify the serial number of the enclosure so a drawing revision can be traced to a delivered unit. That is an evidence requirement. It does not mean every cabinet must be tested to destruction.

Responsibility boundary at handover

The fabricator controls sheet-metal forming, welding, coating and the fitted seal. The buyer or electrical integrator controls site conditions, cable termination and any later drilling. Once a contractor adds a new entry after delivery, the original verification no longer describes the enclosure. The order should say who is allowed to modify the boundary and what must be rechecked.

Realjet does not assign an IP rating to a cabinet by appearance. When an enquiry includes the target code, the entry schedule and the evidence required, the team can quote the fabrication scope against a defined requirement. Where a test or certification is required, the responsible party and the cost are agreed before the order is placed.

What to send in the RFQ

Send the installation conditions, the target code, a dimensioned drawing, the entry schedule, gasket and latch details, finish requirements and the record you expect at delivery. State which items are excluded from the enclosure scope. If the project uses a proprietary cabinet system, provide its drawing and confirm who owns the tooling and the test evidence. With those inputs, contract manufacturing quotes can be compared on the same scope instead of on an assumed level of sealing.