Noise and dust are usually discussed on a precast line after it starts running, when the mixer is too close to the operator cabin and the silo filter discharges onto the walkway. By then the building is built, the equipment is anchored, and the remedy is an enclosure or a ventilation change that nobody budgeted for.

Both are set much earlier, in the equipment schedule and the layout drawing. Both are also measurable, so they can be specified.

Occupational limits are the buyer's duty, not the supplier's

The employer carries the legal duty. What the buyer controls is the equipment that makes the exposure, so the numbers belong in the purchase.

In the European Union, Directive 2003/10/EC sets a daily exposure limit of 87 dB(A) and a peak of 200 Pa, with upper action values of 85 dB(A) and 140 Pa and lower action values of 80 dB(A) and 112 Pa. Exposure limit values are assessed taking the attenuation of hearing protection into account. Action values are not. Workers exposed above 85 dB(A) are entitled to a hearing check, and preventive audiometric testing is offered above 80 dB(A) where the risk assessment shows a risk.

In the United States, OSHA 1910.95 permits 90 dBA for an eight hour day in its Table G-16, and requires a hearing conservation programme at an eight hour time weighted average of 85 dBA, which it calls the action level.

The two regimes differ in the numbers and in how they treat protection, but they point the same way for a buyer: the line has to be quiet enough that the exposure is manageable without relying on protection as the primary control.

Where the noise actually comes from

On a beam or slab line the loudest sources are rarely the ones in the quotation's headline. They are:

  • vibrating tables and form vibrators, especially when the mould is empty
  • internal poker vibrators, which are held by an operator
  • the batching plant mixer, particularly during charging and discharge
  • silo filling and filter cleaning, which is intermittent and easy to miss in a survey
  • compressed air, including pneumatic vibrators, blow-down and nozzle cleaning
  • saws and grinders cutting or dressing hardened concrete
  • crane travel, hoist and travel alarms
  • demoulding and turning equipment, where the impact is short and loud
  • spinning machines on a spun pile line

A survey that measures only the mixer will understate the exposure of the person who stands beside the table all shift. The exposure that matters is the one at the operator position, over a full cycle.

Adjectives do not survive a measurement

"Low noise" is not a specification. Three details decide whether a declared figure means anything.

Sound power and sound pressure are different quantities. Sound power describes the machine. Sound pressure describes the position where a person stands. A supplier can quote a modest sound power level for a machine that puts 95 dB(A) beside the operator because the noise is directed at them. Ask for both, and ask which measurement standard was used.

The load condition matters. A vibrating table is loudest under load. A mixer is loudest during charging. A figure taken at idle, in an empty bay, with the extraction off, describes a machine that never exists in service.

The distance and the height matter. A figure quoted at one metre from the casing, at floor level, is not the figure at the operator's ear.

Dust is a different problem with the same timing

OSHA 1910.1053 sets a permissible exposure limit of 50 micrograms per cubic metre for respirable crystalline silica as an eight hour time weighted average, with an action level of 25. The exposure on a precast line does not come mainly from the fresh concrete. It comes from the cementitious materials before they are mixed, and from cutting or grinding concrete after it has hardened.

The predictable points are silo filling, where displaced air carries cement out of the vent; mixer charging; conveyor transfer points; bag or bulk addition of admixtures and pigments; housekeeping, where dry sweeping puts settled dust back into the air; and any sawing, coring or grinding operation on cured product.

For a new line, the first four are equipment and layout decisions. The last one is a process decision, and it is usually the one that turns into a respiratory protection programme.

The equipment items that carry the answer

These are the scope lines to look for in a proposal, because they are what a supplier can actually price:

  • filter units on every silo and on the mixer, sized for the filling rate rather than the average
  • enclosed or hooded transfer points between silo, weigh hopper and mixer
  • extraction or water mist at the charging point
  • a sealed and, where the climate requires it, air conditioned control cabin positioned away from the table
  • drives and vibrator motors mounted outside the operator zone, or an acoustic hood over the vibrator bank
  • low noise air nozzles in place of open blow-down
  • resilient mounts under vibrating tables and under the batching plant frame
  • rubber or polymer linings in chutes and hoppers, which reduce impact noise as well as wear

Each item has a cost and a maintenance implication. A silo filter that is undersized blocks, and a blocked filter dumps dust at the next filling. That trade-off belongs in the technical review, not in the first week of production.

Where the scope boundary sits

The usual split is that the supplier delivers equipment that meets the declared levels at declared positions, and the buyer provides the building envelope, the general ventilation, the monitoring programme and the hearing protection.

The building is not a minor part of that. A metal clad hall with hard surfaces reflects noise back to the operator. A layout that places the batching plant against a wall, with the operator between the wall and the mixer, is louder than the equipment schedule suggests. This is why the layout and floor space discussion and the noise question are the same conversation, and why the utilities scope should name compressed air quality, since leaking air is both a noise source and a running cost.

Dust follows the same pattern. The batching plant is a dust source as well as a concrete source, so the batching plant interface is where silo vents, filter access and washdown are agreed. Where water is used for dust suppression or washdown, the wash water and slurry handling question follows immediately, because the water has to go somewhere.

What to put in the order

Parameter What to write Why it changes the price
Noise at the operator position dB(A) at named positions, under normal production load, with the standard named Drives enclosure, mounting and cabin decisions
Sound power per machine Declared LwA for each major item, with the standard used Makes figures comparable
Silo and mixer dust Emission limit at the filter outlet, filter area and cleaning method Sizing and service access
Extraction Points served, air volume, where the duct runs Affects layout and duct routes
Clean-up Whether washdown or vacuum is intended, and the drains for it Changes floor falls and drainage
Checking Who measures, when, with which meter, and what happens if a figure is exceeded Prevents a dispute after installation
Operating limits Shift length, parallel operations, maximum number of people in the zone Sets the exposure the design must meet

The verification row is the one that turns a promise into a purchase condition. A measurement taken during commissioning, at the positions named in the contract, with the line running its normal cycle, is the only evidence that the equipment does what the quotation said.

What this looks like before the enquiry

A buyer who arrives with the product list, the shift pattern and the local noise limits gets a proposal that can be checked. Arrive with only a layout and a capacity target, and the proposal will meet the capacity and say nothing about noise or dust.

The precast beam factory planning page sets out how a line is scoped from the product range and the plant, and the staffing question, including who stands where for a full shift, is worth settling at the same time, as the staffing before purchase note describes. Noise and dust are consequences of the layout and the equipment list. Once those are fixed, the only remaining lever is an enclosure.