What subcontracting means in a made-to-drawing order
A buyer places a contract manufacturing order with one supplier and expects one accountable party. The workshop that signs the order may not perform every operation itself. Welding, heat treatment, machining, coating or non destructive testing can pass to another company, sometimes in another country. That arrangement is ordinary in fabrication. It becomes a problem when the buyer learns about it after the order is signed.
What the buyer needs settled is which operations may be moved, who approves the move, and what records come back under the prime contractor's name. Those three points belong in the RFQ, before prices are compared.
This article is written for buyers of welded frames, machined assemblies and equipment structures who need one clear responsibility chain. It does not assume any particular supplier uses subcontractors, and it does not describe Realjet's subcontracting practice. It describes what a buyer should ask and put in writing.
Why the boundary matters before the order
A subcontracted operation changes the inspection route. A weld made in another shop still has to match the procedure, the welder qualification and the acceptance class named in your specification. A machined face produced elsewhere still has to be measured against the same datum the drawing sets. If the purchase order names only the prime contractor, those requirements can arrive at the second shop as a paraphrase.
The cost of a gap appears late. A first article can pass at the subcontractor and then fail at final assembly because the datum used for machining did not match the datum used for welding. A material certificate can cover the plate but not the bought in part fitted downstream. The release pack shows both, if there is one.
Buyers who ask early get a usable answer. A supplier that can name its own in house processes, identify the operations it would source outside, and describe how it controls them is easier to compare with a bidder that answers in generalities. Our guide to qualifying a supplier for made to drawing parts covers the broader check; this article covers one part of it.
The current standards answer
ISO 9001 is the common reference for how an organisation controls externally provided processes. The current edition is ISO 9001:2026, which ISO states now replaces the 2015 edition. ISO also states that the harmonised structure has not changed and that certified organisations have a transition period agreed with their certification body. So a supplier still working to the 2015 certificate is not automatically outside the framework, but the edition named in the order should be the one in force when the work is done.
For welding, ISO 3834-2:2021 defines comprehensive quality requirements for fusion welding in workshops and at field sites. ISO records it as published, confirmed after review in 2026. The standard sets requirements for the welding activity; it does not transfer design authority, and it does not by itself tell a buyer which operations the supplier may move. That decision stays in the contract.
The standards give a method for controlling outside work rather than a list of approved subcontractors. The purchase order has to say which method applies and what evidence the buyer receives.
Four questions to ask every bidder
Keep the questions short and answerable. A long questionnaire gets polished answers that do not settle anything.
- Which operations will you perform in your own works, and which will you place outside?
- For each outside operation, do you notify us before placement or only after?
- Who signs the inspection record for that operation, and in whose name is it issued?
- If the outside shop cannot meet the specification, who pays to put it right?
The fourth question is the one most often skipped. A supplier may accept responsibility for the final assembly while the purchase order is silent on rework caused by a subcontracted process. In practice that ambiguity becomes a variation claim. Put the answer in the order as a sentence, not as an assumption.
The same logic applies to inspection and test plans. A hold point that names the prime contractor's inspector is not the same as a hold point the buyer can witness at the second shop. If the buyer needs access, say so before the slot is booked.
A scope matrix that settles the argument
A single table in the technical annex does more than pages of terms and conditions. One row per operation, with the same column headings sent to every bidder, makes the offers comparable.
| Step | Record issued | Basis |
|---|---|---|
| Cut and form | Fabricator | Approved drawing and tolerance |
| Main welds | Supplier, weld shop | Procedure, welder, ISO 5817 class |
| Heat treat | Treatment provider | Time and temperature chart |
| Machining | Machine shop | Dimensional report from datums |
| Coating | Coater | Preparation and film thickness |
| NDT | Testing provider | Method and acceptance class |
Every row is assumed to be the supplier's own work until the supplier marks it as sourced outside. Mark any such operation and require approval before it happens. Ask for the table to be filled in, not for a statement that all work is controlled. A filled table shows where the buyer's specification has to travel and where it might stop.
Evidence that has to come back with the part
Records are the only proof that a subcontracted operation happened under the right instructions. For welding, that means the procedure reference, the welder qualification, the consumable batch where specified, and the inspection result. Our note on welding procedure and NDT scope sets out how those items are named in an enquiry.
For material, the certificate has to follow the part through every handover. A plate certificate tied to a heat number is useful only if the plate that reached the second shop is the same plate. The material certificates guide explains what the certificate levels prove and what they do not.
For machining, ask for a dimensional report measured from the drawing datums, not a free hand summary of nominal sizes. The machined interfaces guide explains why datum choice decides whether the assembly fits. Where a trial assembly is part of the order, state whether the second shop attends or whether the prime contractor proves the fit on its own floor.
One practical rule: every record should carry the supplier's name, the operation, the part or batch identity and the date. A record issued only by a company the buyer has never heard of is hard to use when a question comes up two years later.
Where the responsibility sits
Design authority stays with the buyer or the designated designer. Geometry, tolerances, material grades and acceptance limits do not become the supplier's decisions because an operation moved to another shop. The prime contractor owns the execution route, including the choice and control of any second party, unless the order says the buyer approves that choice. The buyer owns the approval of deviations and the final acceptance criteria.
That split is worth writing out in the order. It prevents the common claim that a subcontractor's mistake is outside the prime contractor's scope. It also prevents the opposite assumption, that the prime contractor may redesign a feature because the second shop finds it awkward.
How Realjet frames its own scope
Realjet manufactures welded machine frames, structures and equipment supports to customer drawings, with machining of interfaces after fabrication. Its welding quality system is to ISO 3834-2, with EN 15085-2 CL1 for railway work, and its robotic welding covers arc and GMAW processes with post weld cleaning. Bending runs from 3,200 to 6,000 mm at up to 500 t, and machining includes drilling, boring, deburring and sub assembly.
Those are statements about work Realjet performs. They are not statements about which operations, if any, are placed outside, and they are not a promise about a particular order. A buyer who needs a firm answer on that point should ask for it during technical review and have the answer written into the contract. The contract manufacturing service page sets out the made to drawing route; the final scope stays subject to the approved project documents.
Before you release the order
Fill the scope matrix with each bidder, name the records you expect for each operation, and state who approves any change of shop. If a supplier cannot tell you where the work will be done, treat that as an unanswered question rather than a sign of flexibility. A clear chain is worth more at handover than a lower price built on an undefined one.