A welded frame rarely fails because one dimension is out of tolerance. It fails because two features that must line up were each made inside their own tolerance, in opposite directions. A motor pad and a gearbox pad two metres apart can both pass inspection and still leave the coupling out of alignment. The drawing is the only place where that risk can be closed before the quotation is written.

Where the error enters a frame

Four operations put error into a welded frame: cutting the plate, fitting it up, welding it, and machining whatever has to be accurate afterwards. Each has its own tolerance document, and each is usually covered by a different sentence in the purchase order.

Cutting decides the size of the part before anything is joined. Fit-up decides how much gap the welder has to fill, and a wide gap shrinks more than a tight one. Welding adds angular distortion at every fillet and longitudinal shrinkage along every seam. Machining, if the frame gets any, can correct what came before it, but only on the faces the drawing nominates.

Cutting tolerance is already a purchasing decision

ISO 9013 classifies thermal cuts and sets quality tolerances for oxyfuel, plasma and laser cutting. Its scope is specific: flame cuts from 3 mm to 300 mm, plasma from 0.5 mm to 150 mm, laser from 0.5 mm to 32 mm. A 120 mm plate cannot be laser cut, and a 6 mm plate cut by flame will not hold the same edge as the same plate cut by laser.

The standard applies only when the drawing or the delivery conditions refer to it. That matters in practice. If the drawing says nothing about cut quality, the fabricator cuts to workshop practice, and the first time anyone compares two plates is at fit-up.

The weldment has its own tolerance standard

ISO 13920:2023 covers general tolerances for welded constructions, in four classes based on customary workshop accuracy. Two sentences in its scope are worth carrying into an enquiry. The applicable tolerances are always those stated in the drawing. And a manufacturing document that shows dimensions without individual tolerances, but without an adequate reference to general tolerances, is deemed incomplete.

A frame drawing with no general tolerance note leaves the class open, and the fabricator will close it by choosing one. That choice is commercial as much as technical, because a tighter class means more fixturing, more rework and a higher price.

Machining brings a second standard into the same part

ISO 2768-1 sets general tolerances for linear and angular dimensions without individual indications, again in four classes, and it applies to parts produced by metal removal or formed from sheet metal. It was last confirmed in 2022 and is expected to be replaced by a revised ISO 2768, so the edition matters when a drawing is reused on a later order.

Mixing the two documents is where errors start. A weldment toleranced to ISO 13920 and then machined to ISO 2768 is workable, but the drawing has to say which faces follow which document. When it does not, the machinist reads "general tolerance" as the one printed in the title block, and the fabricator reads the same note as applying to the welded assembly.

Deciding which datum the machinist works from

Machining interfaces after fabrication is how a welded frame reaches the accuracy a machine needs. Geometrical tolerancing gives the drawing the language for it: flatness on a pad, position on a hole pattern, perpendicularity of a machined face to a datum.

The datum scheme has to survive the welding. If the drawing datums a machined face that only exists after machining, the fabricator has nothing to measure against at fit-up. The practical answer is usually a pair of datums: rough datums used during fabrication, and final datums established at machining, with the relationship between them defined on the drawing. Machined interfaces covers how that scope is quoted.

Machining allowance belongs in the same conversation. A pad that is flame cut and then faced needs extra thickness, and the amount depends on how much distortion the weld is expected to cause. Without a stated allowance, the machinist takes a light cut to clean up the surface, and a pad that started 2 mm under nominal ends up thinner than the design assumed.

What stacking does over a long frame

General tolerances are written for individual dimensions. On a frame, the dimension that often matters is the distance between two features, each of which was made to its own tolerance. Three pads at two metre centres, each within plus or minus 2 mm of position, can put the outer two pads 4 mm apart from the nominal distance in the worst case, before any welding distortion is added.

Two methods are used to handle that. Worst case adds every contributor arithmetically and assumes they all go the same way. Statistical stacking assumes the errors are independent and adds them as a root sum of squares. Neither is prescribed by the standards above. What matters for the buyer is that the drawing names the functional dimensions, the ones that carry a direct tolerance because the assembly depends on them, and leaves general tolerance to everything else.

Bolt hole tolerance and fit-up is a related problem at the joint itself. Stack-up is the same problem between sub-assemblies.

What to put on the drawing and in the order

Item What to state Why it matters
Weldment tolerance Standard, edition and class for the welded frame Removes the fabricator's default choice
Cut quality Standard and class for plate edges, with the thickness range Separates an achievable cut from a grinding operation
Machined features Which faces are machined, and to which standard Stops two tolerance systems being applied by accident
Datums Rough datums for fabrication, final datums for machining Gives both stages a reference they can measure
Allowance Material left on pads for machining Protects the finished thickness
Sequence Whether stress relief or galvanizing happens before or after machining A thermal cycle or a coating after machining moves the surface
Records Which dimensions are measured, and by what method Makes the inspection report comparable to the drawing

Sequence is the row most often missed. Stress relief before machining releases distortion while there is still material to remove. Galvanizing after machining keeps the machined faces clean, but the dip adds a zinc layer that changes the fit on a machined pad unless the drawing allows for it.

What the inspection report should contain

A dimensional report is only useful if its method is stated. A tape measure, a laser tracker and a boring mill's own scale will not agree on a six metre frame, and a report that lists numbers without saying how they were taken cannot settle a dispute at site.

First article inspection is the stage where this is normally fixed: one frame is measured in full, the report is compared with the drawing, and any concession is agreed before the rest of the batch is built. For a one-off frame, the same report is the final inspection, and it is worth naming it as a deliverable in the order rather than asking for it at dispatch.

What happens when a dimension misses needs a clause as well. A frame that is 3 mm over on an overall length may be usable, and scrapping it is wasteful. A frame that is 3 mm over on a bearing centre distance may not be. The concession route, including who decides and what evidence is required, is cheaper to agree when the order is placed than when the frame is on the floor.

What Realjet can be held to

Realjet fabricates welded frames, structures and equipment supports to customer drawings, with machining of interfaces after fabrication. Welding is controlled to ISO 3834-2, with EN 15085-2 CL1 for railway work and robotic arc and GMAW welding with post-weld cleaning. Bending runs from 3,200 to 6,000 mm at up to 500 t, and the machining scope covers drilling, boring, deburring and sub-assembly.

Which tolerance standard applies, which faces are machined and what the inspection record contains are settled during technical review and confirmed in the quotation. The contract manufacturing page sets out the service scope. Stack-up is settled on the drawing before the order, or in a dispute after the frame is painted.