A caisson is usually the largest single element a precast yard will ever cast, and it is almost never cast in one operation. It rises in stages, each stage poured against the one below, with a construction joint between them and a set of internal cell forms that has to come out again after every pour.

A caisson mould is priced off that sequence rather than off the outline drawing. Two bidders can quote the same tonnage of steel and deliver very different results, because one has priced a form that climbs in four lifts and the other has priced a set of fixed panels that have to be craned apart each time.

The casting sequence sizes the mould

The MOSE barrier gates in the Venice lagoon give a published example of how far a caisson sequence can be broken down. Each gate caisson was completed in 15 to 23 casting phases depending on size, with individual pours between 100 and 450 m³, except the bottom slab, where about 1,000 m³ went in as a single pour. Horizontal joints were placed to coincide with the major horizontal elements of the structure, and vertical joints followed a checkerboard scheme of 3 by 3 fields in plan (IOP Conference Series).

Those numbers are the mould brief. Every phase boundary is a face the formwork has to create, and every change of phase is a set-up the yard has to repeat. A buyer who sends an outline and a volume is asking the supplier to invent that sequence, and will get a price built on the supplier's assumption rather than the plant's capability.

Lift height sets the panel height and the platform level

Once the sequence is fixed, the lift height follows, and with it the height of the outer form panels and the level of the working platform. Climbing formwork guidance for tall concrete lifts puts the usual lift at 3 to 6 m, most often 4 to 5 m, with the platforms arranged so that the reinforcement deck sits above the form and a finishing platform trails below (climbing and jump formwork reference). A precast yard has more freedom than a bridge pier, because the form can be craned off and re-set, but the same trade-off applies: taller lifts mean fewer joints and heavier panels, shorter lifts mean more joints and more crane hours.

Panel weight then has to be checked against the yard crane at the radius it will actually work, not at its maximum rating. The mould weight and lifting points question is part of this same decision.

Where the horizontal joint falls is a mould decision

Where the joint falls is a structural decision. How the joint face is formed is a mould decision, and the two are usually made by different people.

A joint face carries the tie holes from the lift below, the form panel split line, any waterstop or shear key, and the surface preparation that the next lift needs. If the waterstop runs through the tie positions, the ties have to move. If the panel split line falls where the designer wanted a smooth face, the line will be visible in the finished element for its whole service life.

The MOSE joint layout shows the point: the horizontal joints were aligned with the major horizontal elements precisely so that the joint would be hidden in a feature rather than left in the middle of a wall. Aligning form panels to that logic is a drawing exercise, and it belongs in the mould approval drawing set rather than in a site instruction.

Cell forms and the withdrawal sequence

A hollow caisson has internal cells, and the internal forms have to be removed from inside a structure that is already partly built. The sequence is decided by cell geometry: which direction each panel can move, how much clearance it needs, and whether the form collapses in place or is lifted out in pieces.

Published yard practice shows the range. One wharf project cast 67 caissons using horizontal stratification, with the upper side mould divided into eight pieces and four inner mould sections connected by a lifting frame so that they came out as one unit (project description). A Japanese development went further and used permanent precast concrete forms, eliminating form removal altogether and cutting fabrication time from 50.6 to 25.8 days (JSCE, PDF).

Each approach produces a different mould order, and the outline alone does not distinguish between them.

Verticality accumulates and cannot be corrected in one lift

Each lift is set out from the one below, so a small lean at the third lift is a larger lean at the tenth, and the correction has to be spread over several lifts rather than taken out in one. Climbing formwork practice surveys position, verticality and twist at a fixed time of day on every lift and corrects the drift gradually.

The same discipline applies in a yard, with an added complication: the form is re-set between lifts, so the reference has to survive the set-up. That means permanent reference points on the element or on the casting bed, recorded before each pour, and a tolerance basis that the buyer and supplier have agreed in advance. Mould tolerances for a production line order sets out what that basis should contain.

Wall thickness and cover belong to the same conversation. In the MOSE caissons the cover was held at 4 to 5 cm with stainless steel in the most exposed zones, which is a specification the internal and external forms both have to respect, not just the drawing.

Cycles decide how many form sets

Formwork cost per element is the total cost divided by the number of uses. A caisson programme of 20 units and a programme of two units need different answers, even when the geometry is identical.

The JSCE paper makes the economics explicit: the precast form caisson saved about 75 percent of the labour and half the fabrication time, and yet the total cost came out at 99.4 percent of the conventional method, because the forms were expensive and only one caisson was built with them. MOSE ran two to three caissons in parallel to keep the prefabrication programme inside two years, with each unit taking six to nine months.

For a buyer, the question is therefore how many form sets the programme justifies. One set plus a long programme means the form is worked hard and the joints are consistent. Several sets mean the programme finishes sooner and the capital sits idle afterwards. Mould modification or new build is the follow-on question when a second project arrives with similar geometry.

Weight, launch and the handling interface

A finished caisson is launched, floated or lifted, and the mould has to leave that operation possible. Casting in a basin or on a slipway, jacking the unit onto a floating dock, and lifting by crane all impose different requirements on lifting points, base geometry and the sequence in which temporary works are removed.

At the Tuas reclamation project in Singapore, the base slab took three to five days to build with about 300 tonnes of reinforcement, the walls then rose in a slipform operation over 84 to 88 hours, and the finished caisson was launched onto a floating dock (project report). A slipform and a climbing panel set are different moulds with different orders behind them, and the launch method is part of what decides which one is appropriate.

What to put in the enquiry

Input What to send What it decides
Casting sequence Number of lifts, pour volumes, joint levels Panel heights, set-up count, cycle time
Joint detail Waterstop, shear key, surface preparation Joint face design and tie positions
Cell layout Number of cells, sizes, wall thickness Internal form division and withdrawal direction
Tolerance basis Verticality, wall thickness, cover, survey points Setting-out method and inspection records
Programme Units required and dates Number of form sets and the reuse assumption
Handling Lift, launch or float, lifting points Base geometry and temporary works interfaces
Access Platforms, stairs, guardrails, lighting Whether access is in the mould scope
Concrete Mix, placement rate, vibration method Panel pressure, stiffener spacing, pour limits

The row that changes the price most is the casting sequence. It is also the row most often left to the supplier, which is why two quotations for the same caisson outline can differ for reasons that have nothing to do with the price of steel.

Where this fits Realjet's scope

Realjet builds steel moulds for precast concrete units around the approved component drawing, the casting method and the plant layout, with dimensional records agreed against that drawing. Caisson work sits in the marine and coastal moulds range, alongside armour units and tetrapods.

The precast concrete caisson moulds page sets out the configurations used for large hollow marine structures: modular outer and internal form panels, repositionable form sections for repeated stages, and project specific working platform interfaces. The caisson mould RFQ guide covers the commercial side of the same order, including the interface schedule that keeps yard works in the right scope.