The first question a plant planner asks about a circulation line is how many pallets it needs. The number that comes back is usually a single figure, and that figure is usually wrong, because two different counts are being answered with one number.

One count is the pallets travelling through the line: the ones under the concrete distributor, at the plotter, at the demoulding station. The other is the positions inside the curing chamber, which is often several times larger. A buyer who treats the second as part of the first will order a line that either cannot cure what it casts or carries a fleet it never uses.

Pallets and curing positions are two different counts

A circulation line is a loop of pallets passing a fixed sequence of stations at a fixed rhythm. Pallets leave the loop to enter the curing chamber, wait there while the concrete gains strength, and rejoin it for demoulding.

So the fleet divides into three parts. Pallets in the working zone are bounded by the number of stations a pallet can occupy at once. Pallets inside curing are bounded by how long curing takes against the rhythm of the line. A buffer of one or two pallets covers the case where a single station stops and the pour must not.

Published plant descriptions show the same split. A German solid wall plant was planned with 40 pallets of 13.5 by 4.35 m and built with 36, producing 42 walls and about 870 m² in a ten hour shift with 20 operators, and it uses a five pallet curing tunnel as a buffer ahead of the smoothing line (Reymann Technik). A plant for large double and solid walls runs 40 pallets of 16.20 by 3.70 m through 12 workstations with 34 curing bays (Prilhofer Consulting). In both cases the two numbers differ, and the difference is the working zone.

The arithmetic behind the fleet

The line runs at a takt, which is the time between two finished elements. Divide the available working minutes in a shift by the number of elements required and you have the takt. If a shift offers 600 minutes and the plant needs 60 elements, the takt is 10 minutes.

Curing positions then follow from the cure time expressed in takts. Eight hours of curing is 480 minutes, which is 48 takts at a 10 minute rhythm, so the chamber needs about 48 occupied positions at steady state. Working pallets are simpler: one per station that a pallet occupies simultaneously, plus the transfer positions, so a ten station line needs about ten to twelve.

The fleet is the sum. That is why a published carousel of 52 pallets with 48 curing spaces reads as plausible: the four pallet difference is the working zone, and the line is balanced. A plant ordered with 52 pallets and 20 curing spaces would be a different machine, running slower and casting less.

Where the cure time comes from

Cure time is often treated as a property of the mix. What sets it is the strength needed to strip and handle the element, and how quickly the concrete reaches that strength. Cement type, water to cement ratio, admixtures, ambient temperature and whether the chamber is heated all move the number.

The values in published plants vary accordingly. A plant in a warm climate takes pallets out of a 15 pallet rack after four hours (Ratec project report, PDF). A high speed carousel in a temperate climate handles four to six pallets an hour with an insulated chamber of four towers holding up to 18 pallets each, so 72 positions in total (Kraft Curing). Both are the same principle with different constants.

For the buyer, the consequence is that the curing count cannot be fixed until the mix and the curing regime are fixed. A line ordered on a summer cure time will be short of positions in winter unless the chamber can be heated or the takt relaxed. Curing system RFQ inputs covers the equipment side of that decision, and cycle time and daily output works through the same arithmetic for a beam line.

Pallet size sets the hall, the fleet sets the working capital

Pallet dimensions are chosen around the largest element the plant expects to cast, with a margin for moulds, magnets and clamping. Published sizes run from 10.0 by 3.0 m to 16.2 by 3.7 m, and the difference is not cosmetic: it decides the hall width, the crane span, the size of the curing chamber doors and the load on the transfer equipment.

Fleet size then multiplies that footprint. Forty pallets of 16.2 by 3.7 m occupy about 2,400 m² of pallet surface, which has to exist as hall floor, chamber volume and storage at the same time. A buyer who fixes the pallet size before the product range is settled tends to buy too much steel in the pallet and too little in the chamber. Floor space planning treats the hall dimensions as the constraint rather than the outcome.

Buffer, bypass and the stations that stop the line

Two details in the published plants are worth copying into an enquiry. The first is a buffer ahead of a slow station, so that pallets can queue without blocking the pour. The second is a bypass at the demoulding station, so that a pallet being stripped does not hold up the ones behind it.

Neither is free. A bypass adds a transfer and a length of line. A buffer tunnel adds pallets and heat. Both are cheaper to include at order stage than to retrofit into a hall whose columns are already in place.

What a short fleet actually costs

Too few pallets does not show up as a broken machine. It shows up as a line that runs at the speed of its slowest handover, with the distributor waiting while a pallet is still being cleaned, and with operators standing idle between pours. The plant then buys pallets later, at a unit price that no longer includes the original engineering, and discovers that the chamber is the real constraint anyway.

Too many pallets has its own cost. Every pallet is capital, floor area and maintenance, and an oversized fleet hides the fact that the chamber, not the loop, limits output. The useful check before signing is to ask the supplier to show the steady state: how many pallets are in the working zone, how many in curing, and what the line does when one station stops for 20 minutes.

What to put in the enquiry

Input What to send What it decides
Product range Element types, largest plan size and thickness Pallet dimensions and mould fixing system
Output Elements per shift and shifts per day Takt, and therefore the whole fleet
Cure regime Mix family, stripping strength, chamber temperature Curing positions, often the largest number
Shift pattern Hours per shift, breaks, maintenance window Available working minutes and realistic takt
Buffer policy Accepted queue in front of slow stations Extra pallets and bypass stations
Future products Elements planned within five years Whether to size up now or leave room
Handling Crane capacity, lifting devices, stacking Pallet weight, lifting points, chamber height
Hall Available length, width, clear height, columns Pallet size and line layout

The row buyers most often answer from memory is cure regime. It is the one that sets the largest number in the order, and it is worth a trial mix rather than an assumption.

Where this fits Realjet's scope

Realjet delivers precast production lines as project packages covering casting equipment, moulds and the interfaces to batching, curing and handling, with the pallet fleet sized against the product range and the output target rather than a catalogue default. The precast beam factory pages describe the long line and beam side of that work, and wall and slab production lines cover the circulation plants where this question usually arises.

Two related articles go further into the same decision. Fixed or circulation lines covers the choice of concept before the fleet is sized, and how many moulds a line needs applies similar arithmetic to the mould count, which is a separate constraint on the same rhythm.